[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908526":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908526,587,1,"单选题","（2017年考题）施工图预算审查方法中，审查速度快，但审查精度较差的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","标准预算审查法",false,{"key":16,"text":17,"correct":14},"B","对比审查法",{"key":19,"text":20,"correct":21},"C","分组计算审查法",true,{"key":23,"text":24,"correct":14},"D","全面审查法","分组计算审查法：其优点是可加快工程量审查的速度；缺点是审查的精度较差。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]