[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908523":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908523,587,1,"单选题","（2017年考题）根据《标准施工招标文件》合同双方发生争议采用争议评审的,除专用合同条款另有约定外,争议评组应在( )內做出书面评审意见。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","收到争议评审申请请报告后28 天",false,{"key":16,"text":17,"correct":14},"B","收到被申请人答辩报告后28 天",{"key":19,"text":20,"correct":21},"C","争议调查会结束后14 天",true,{"key":23,"text":24,"correct":14},"D","收到合同双方报告后14 天","考查《标准施工招标文件》争议评审组。除专用合同条款另有约定外，争议评审组在收到合同双方报告后的 14 天内，邀请双方代表和有关人员举行调查会，向双方调查争议细节;必要时争议评审组可要求双方进一步提供补充材料。在调查会结束后的 14 天内，争议评审组应在不受任何干扰的情况下进行独立、公正的评审，做出书面评审意见，并说明理由。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]