[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908516":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908516,587,1,"单选题","(2016年)招标人在施工招标文件中规定了暂定金额的分项内容和暂定总价款时，投标人可采用的报价策略是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","适当提高暂定金额分项内容的单价",true,{"key":16,"text":17,"correct":18},"B","适当减少暂定金额中的分项T程量",false,{"key":20,"text":21,"correct":18},"C","适当降低暂定金额分项内容的单价",{"key":23,"text":24,"correct":18},"D","适当增加暂定金额中的分项工程量","该题主要考察的是：暂定金额的报价 ，招标单位规定了暂定金额的分项内容和暂定总价款，并规定所有投标单位都必须在总报价中加入这笔固定金额，但由于分项工程量不很准确，允许将来按投标单位所报单价和实际完成的工程量付款。这种情况下，由于暂定总价款是固定的，对各投标单位的总报价水平竞争力没有任何影响，因此，投标时应适当提高暂定金额的单价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]