[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908515,587,1,"单选题","(2016年)根据《标准施工招标文件》，对于施工现场发掘的文物，发包人、监理人和承包人应按要求采取妥善保护措施，由此导致的费用增加应由()承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","承包人和发包人",{"key":23,"text":24,"correct":14},"D","发包人和监理人","该题主要考察的是：合同涉及费用的主要条款，在施工场地发掘的所有文物、古迹以及具有地质研究或考古价值的其他遗迹、化石、钱币或物品属于国家所有。一旦发现上述文物，承包人应采取有效合理的保护措施，防止任何人员移动或损坏上述物品，并立即报告当地文物行政部门，同时通知监理人。发包人、监理人和承包人应按文物行政部门要求采取妥善保护措施，由此导致费用增加和（或）工期延误由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]