[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908512,587,1,"单选题","(2014年)对施工承包单位而言，承担风险大的合同计价方式是（ ）方式。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总价",true,{"key":16,"text":17,"correct":18},"B","单价",false,{"key":20,"text":21,"correct":18},"C","成本加百分比酬金",{"key":23,"text":24,"correct":18},"D","成本加固定酬金","本题考查的是合同计价方式。在总价方式中，建设单位造价控制比较容易，但施工承包单位要承担的风险会很大。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]