[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908509,587,1,"单选题","(2013年)下列不同计价方式的合同中，施工承包单位承担风险相对较大的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本加固定酬金合同",false,{"key":16,"text":17,"correct":14},"B","成本加浮动酬金合同",{"key":19,"text":20,"correct":14},"C","单价合同",{"key":22,"text":23,"correct":24},"D","总价合同",true,"该题主要考察的是：施工合同计价方式。表6.3.2 不同计价方式的合同比较中施工合同中，计价方式可分为三种，即总价方式、单价方式和成本加酬金方式。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]