[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908486":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908486,587,1,"单选题","(2016年)工程项目策划中，需要通过项目定位策划确定工程项目的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","系统框架",false,{"key":16,"text":17,"correct":14},"B","系统组成",{"key":19,"text":20,"correct":21},"C","规格和档次",true,{"key":23,"text":24,"correct":14},"D","用途和性质","工程项目的定位是根据市场需求，综合考虑投资能力和最有利的投资方案，决定工程项目的规格和档次。在工程项目定义和定位明确的前提下，需要提出工程项目系统框架，进行工程项目功能分析，确定工程项目系统组成。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]