[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908480":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908480,587,1,"单选题","(2014年)工程项目经济评价中，财务分析依据的基础数据是根据（ ）确定的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","完全市场竞争下的价格体系",false,{"key":16,"text":17,"correct":14},"B","影子价格和影子工资",{"key":19,"text":20,"correct":14},"C","最优资源配置下的价格体系",{"key":22,"text":23,"correct":24},"D","现行价格体系",true,"该题主要考察的是：工程项目经济评价，财务分析是在国家现行财税制度和价格体系的前提下，从项目的角度出发，计算项目范围内的财务效益和费用，分析项目的盈利能力和清偿能力，评价项目在财务上的可行性。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]