[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908478":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908478,587,1,"单选题","(2013年)在工程项目财务分析和经济分析中，下列关于工程项目投入和产出物价值计量的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经济分析采用影子价格计量，财务分析采用预测的市场交易价格计量",true,{"key":16,"text":17,"correct":18},"B","经济分析采用预测的市场交易价格计量，财务分析采用影子价格计量",false,{"key":20,"text":21,"correct":18},"C","经济分析和财务分析均采用预测的市场交易价格计量",{"key":23,"text":24,"correct":18},"D","经济分析和财务分析均采用影子价格计量","该题主要考察的是：财务分析与经济分析的区别 两种分析中衡量费用和效益的价格尺度不同。项目财务分析关注的是项目的实际货币效果，它根据预测的市场交易价格去计量项目投入和产出物的价值，而项目经济分析关注的是对国民经济的贡献，采用体现资源合理有效配置的影子价格去计量项目投入和产出物的价值。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]