[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908450,587,1,"单选题","（2017年考题）为确保政府财政承受能力,每一年全部PPP 项目需要从预算中安排的支出占一股公共预算支出的比例,应当不超过（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","15%",{"key":19,"text":20,"correct":21},"C","10%",true,{"key":23,"text":24,"correct":14},"D","5%","考查PPP 模式，新增内容，一般都会讲到这个数10%",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]