[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908434":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908434,587,1,"单选题","(2014年)投保安装工程一切险时，安装施工用机器设备的保险金额应按（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际价值",false,{"key":16,"text":17,"correct":14},"B","损失价值",{"key":19,"text":20,"correct":21},"C","重置价值",true,{"key":23,"text":24,"correct":14},"D","账面原值","本题考查的是安装工程一切险。安装工程项目， 是指承包工程合同中未包含的机器设备安装工程项目。 该项目的保险金额为其重置价值。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]