[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908416":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908416,587,1,"单选题","(2018年)PPP 项目财政承受能力论证中，确定年度折现率时应考虑财政补贴支出年龄，并参照（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","行业基准收益率",false,{"key":16,"text":17,"correct":14},"B","同期国债利率",{"key":19,"text":20,"correct":21},"C","同期地方政府债券收益率",true,{"key":23,"text":24,"correct":14},"D","同期当地社会平均利润率","财政运营补贴周期指财政提供运营补贴的年数。年度折现率应考虑财政补贴支出发生年份，并参照同期地方政府债券收益率合理确定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]