[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908400,587,1,"单选题","(2015年)根据项目融资程序，评价项目风险因素应在( )阶段进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投资决策分析",false,{"key":16,"text":17,"correct":14},"B","融资评判",{"key":19,"text":20,"correct":14},"C","融资决策分析",{"key":22,"text":23,"correct":24},"D","融资结构分析",true,"本题考查的是项目融资的特点和程序。融资结构设计阶段的内容：评价项目风险因素、评价项目的融资结构和资金结构，修正项目融资结构。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]