[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908378":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908378,587,1,"单选题","（2017年考题）项目公司为了扩大项目规模往往需要追加筹集资金,用来比较选择追加筹资方案的重要依据是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","个别资金成本",false,{"key":16,"text":17,"correct":14},"B","综合资金成本",{"key":19,"text":20,"correct":14},"C","组合资金成本",{"key":22,"text":23,"correct":24},"D","边际资金成本",true,"考查资金成本的作用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]