[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908365":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908365,587,1,"单选题","(2010年)工程寿命周期成本分析方法的局限性是假定工程对象有()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定的运行效率",false,{"key":16,"text":17,"correct":14},"B","确定的投资额",{"key":19,"text":20,"correct":21},"C","确定的寿命周期",true,{"key":23,"text":24,"correct":14},"D","固定的功能水平","工程寿命周期成本分析法的局限性包括：①假定项目方案有确定的寿命周期；②由于在项目寿命周期早期进行评价，可能会影响评价结果的准确性；③进行工程寿命周期成本分析的高成本使得其未必适用于所有的项目；④高敏感性使其分析结果的可靠性、有效性受到影响。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]