[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908363,587,1,"单选题","(2012年)对生产性项目进行寿命周期成本评价时，可列入工程系统效率的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","研究开发费",false,{"key":16,"text":17,"correct":14},"B","备件库存资金",{"key":19,"text":20,"correct":14},"C","生产阶段劳动力成本节省额",{"key":22,"text":23,"correct":24},"D","生产阶段材料成本降低额",true,"系统效率是投入寿命周期成本后所取得的效果或者说明任务完成到什么程度的指标。如以寿命周期成本为输入，则系统效率为输出。通常，系统的输出为经济效益、价值、效率（效果）等。选项A、B、C应属于费用效率的分母要素。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]