[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908362,587,1,"单选题","(2013年)工程寿命周期成本分析中，为了权衡设置费与维修费之间关系，采用的手段是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行充分研发，降低制造费用",false,{"key":16,"text":17,"correct":18},"B","购置备用构件，提高可修复性",true,{"key":20,"text":21,"correct":14},"C","提高材料周转速度，降低生产成本",{"key":23,"text":24,"correct":14},"D","聘请操作人员，减少维修费用","选项A是设置费中各项费用之间的权衡分析；选项C是系统效率和寿命周期成本之间进行权衡时采取的手段；选项D是维持费中各项费用之间的权衡分析。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]