[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908352,587,1,"单选题","(2018年)价值工程应用对象的功能评价值是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可靠地实现要求功能的最低成本",true,{"key":16,"text":17,"correct":18},"B","价值工程应用对象的功能与现实成本之比",false,{"key":20,"text":21,"correct":18},"C","可靠地实现用户要求功能的最高成本",{"key":23,"text":24,"correct":18},"D","价值工程应用对象的功能重要性系数","对象的功能评价值F (目标成本）,是指可靠地实现用户要求功能的最低成本，它可以理解为是企业有把握，或者说应该达到的实现用户要求功能的最低成本。从企业目标的角度来看，功能评价值可以看成是企业预期的、理想的成本目标值。功能评价值一般以货币价值形式表达。功能的现实成本较易确定，而功能评价值较难确定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]