[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908333,587,1,"单选题","(2016年)工程建设实施过程中，应用价值工程的重点应在()阶段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","勘察",false,{"key":16,"text":17,"correct":18},"B","设计",true,{"key":20,"text":21,"correct":14},"C","招标",{"key":23,"text":24,"correct":14},"D","施工","对于大型复杂的产品，应用价值工程的重点是在产品的研究、设计阶段，产品的设计图纸一旦完成并投入生产后，产品的价值就已基本确定，这时再进行价值工程分析就变得更加复杂。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]