[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908312,587,1,"单选题","（2019年）将投资方案经济效果评价方法划分为静态评价方法和动态评价方法的依据是计算是否考虑了（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","通货膨胀",false,{"key":16,"text":17,"correct":18},"B","资金时间价值",true,{"key":20,"text":21,"correct":14},"C","建设期利息",{"key":23,"text":24,"correct":14},"D","建设期长短","按是否考虑资金时间价值，经济效果评价方法又可分为静态评价方法和动态评价方法。静态评价方法是不考虑资金时间价值，其最大特点是计算简便，适用于方案的初步评价，或对短期投资项目进行评价，以及对于逐年收益大致相等的项目评价。动态评价方法考虑资金时间价值，能较全面地反映投资方案整个计算期的经济效果。因此，在进行方案比较时，一般以动态评价方法为主。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]