[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908279":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908279,587,1,"单选题","(2010年)在工程经济分析中，以投资收益率指标作为主要决策依据，其可靠性较差的原因在于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","正常生产年份的选择比较困难",true,{"key":16,"text":17,"correct":18},"B","计算期的确定比较困难",false,{"key":20,"text":21,"correct":18},"C","未考虑投资回收后的经济效果",{"key":23,"text":24,"correct":18},"D","需要事先确定基准收益率","投资收益率指标的经济意义明确、直观，计算简便，在一定程度上反映了投资效果的优劣，可适用于各种投资规模。但不足的是，没有考虑投资收益的时间因素，忽视了资金具有时间价值的重要性；指标计算的主观随意性太强，换句话说，就是正常生产年份的选择比较困难，如何确定带有一定的不确定性和人为因素。因此，以投资收益率指标作为主要的决策依据不太可靠。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]