[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908278":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908278,587,1,"单选题","(2011年)项目敏感性分析方法的主要局限是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算过程比盈亏平衡分析复杂",false,{"key":16,"text":17,"correct":18},"B","不能说明不确定因素发生变动的可能性大小",true,{"key":20,"text":21,"correct":14},"C","需要主观确定不确定性因素变动的概率",{"key":23,"text":24,"correct":14},"D","不能找出不确定因素变动的临界点","但敏感性分析也有其局限性，它不能说明不确定因素发生变动的情况的可能性大小，也就是没有考虑不确定因素在、未来发生变动的概率，而这种概率是与项目的风险大小密切相关的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]