[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908277,587,1,"单选题","(2011年)以生产能力利用率表示的项目盈亏平衡点越低，表明项目建成投产后的()越小。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","盈利可能性",false,{"key":16,"text":17,"correct":14},"B","适应市场能力",{"key":19,"text":20,"correct":14},"C","抗风险能力",{"key":22,"text":23,"correct":24},"D","盈亏平衡总成本",true,"盈亏平衡点反映了项目对市场变化的适应能力和抗风险能力。从图4. 2. 9 可以看出，盈亏平衡点越低，达到此点的盈亏平衡产量和收益或成本也就越少，项目投产后盈利的可能性越大，适应市场变化的能力越强，抗风险能力也越强。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]