[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908276,587,1,"单选题","(2011年)总投资收益率指标中的收益是指项目建成后()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","正常生产年份的年税前利润或运营期年平均税前利润",false,{"key":16,"text":17,"correct":14},"B","正常生产年份的年税后利润或运营期年平均税后利润",{"key":19,"text":20,"correct":21},"C","正常生产年份的年息税前利润或运营期年平均息税前利润",true,{"key":23,"text":24,"correct":14},"D","投产期和达产期的盈利总和","1)总投资收益率（ROI）。表示项目总投资的盈利水平。 ROI ＝EBIT\u002FTI×100% (4.2.2) 式中： EBIT－项目达到设计生产能力后正常年份的年息税前利润或运营期内年平均息税前利润； TI－ 项目总投资。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]