[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908275,587,1,"单选题","(2011年)在分析工程项目抗风险能力时，应分析工程项目在不同阶段可能遇到的不确定性因素和随机因素对其经济效果的影响，这些阶段包括工程项目的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","策划期和建设期",false,{"key":16,"text":17,"correct":18},"B","建设期和运营期",true,{"key":20,"text":21,"correct":14},"C","运营期和拆除期",{"key":23,"text":24,"correct":14},"D","建设期和达产期","(4）抗风险能力分析。分析投资方案在建设期和运营期可能遇到的不确定性因素和随机因素对项目经济效果的影响程度，考察项目承受各种投资风险的能力。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]