[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908242,587,1,"单选题","(2013年)某工程建设期2年，建设单位在建设期第1年初和第2年初分别从银行借入资金600万元和400万元，年利率8%，按年计息，建设单位在运营期第3年末偿还贷款500万元后，自运营期第5年末应偿还()万元才能还清贷款本息。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","925.78",false,{"key":16,"text":17,"correct":14},"B","956.66",{"key":19,"text":20,"correct":21},"C","1079.84",true,{"key":23,"text":24,"correct":14},"D","1163.04","建设期：第一年末本息和=600×(1+8%)=648（万元）；第二年末本息和=(648+400)×(1+8%)=1131.84（万元）。运营期：第三年末的本息和=1131.84×(1+8%)3=1425.79（万元）；第五年末应偿还的本息和=(1425.79-500)×(1+8%)2=1079.84（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]