[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908235,587,1,"单选题","（2019年）双代号网络计划中关于关键节点的说法正确的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键工作两端的节点必然是关键节点",true,{"key":16,"text":17,"correct":18},"B","关键节点的最早时间与最迟时间必然相等",false,{"key":20,"text":21,"correct":18},"C","关键节点组成的线路必然是关键线路",{"key":23,"text":24,"correct":18},"D","两端是关键节点的工作必然是关键工作","在双代号网络计划中，关键线路上的节点称为关键节点。关键工作两端的节点必为关键节点，但两端为关键节点的工作不一定是关键工作。关键节点的最迟时间与最早时间的差值最小。特别是当网络计划的计划工期等于计算工期时，关键节点的最早时间与最迟时间必然相等。关键节点必然处在关键线路上，但由关键节点组成的线路不一定是关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]