[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908234,587,1,"单选题","(2018年)为缩短工期而采取的进度计划调整方法中，不需要改变网络计划中工作间逻辑关系的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","将顺序进行的工作改为平行工作",false,{"key":16,"text":17,"correct":14},"B","重新划分施工段组织流水施工",{"key":19,"text":20,"correct":21},"C","采取措施压缩关键工作持续时间",true,{"key":23,"text":24,"correct":14},"D","将顺序进行的工作改为搭接工作","工期优化的方法。（1）不改变网络计划中各项工作之间的逻辑关系；（2）压缩关键工作的持续时间；（3）不能将关键工作压缩成非关键工作；（4）各条关键线路的总持续时间压缩相同数值。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]