[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908233,587,1,"单选题","(2018年)工程网络计划中，对关键线路的描述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号网络计划中由关键节点组成",false,{"key":16,"text":17,"correct":18},"B","单代号网络计划中时间间隔均为0",true,{"key":20,"text":21,"correct":14},"C","双代号时标网络计划中无虚工作",{"key":23,"text":24,"correct":14},"D","单代号网络计划中由关键工作组成","本题考查关键线路的确定。(1)利用关键工作确定关键线路。如前所述，总时差最小的工作为关键工作。将这些关键工作相连，并保证相邻两项关键工作之间的时间间隔为零而构成的线路就是关键线路。(2)利用相邻两项工作之间的时间间隔确定关键线路。从网络计划的终点节点开始，逆着箭线方向依次找出相邻两项工作之间时间间隔为零的线路就是关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]