[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908232,587,1,"单选题","(2018年)某工程网络计划中，工作M 有两项紧后工作，最早开始时间分别为12 和13.工作M 的最早开始时间为8，持续时间为3，则工作M 的自由时差为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","本工作自由时差=min（紧后工作的最早开始时间）-本工作最早完成时间= min （紧后工作的最早开始时间）-（本工作最早开始+本工作持续时间）=min（12、13）-（8+3）=12-11=1.",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]