[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908230,587,1,"单选题","（2017年考题）工程网络计划资源优化的目的是通过改变（ ），使资源按照时间的分布符会优化目标。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作间逻辑关系",false,{"key":16,"text":17,"correct":14},"B","工作的持续时间",{"key":19,"text":20,"correct":21},"C","工作的开始时间和完成时间",true,{"key":23,"text":24,"correct":14},"D","工作的资源强度","资源优化的目的是通过改变工作的开始时间和完成时间，使资源按照时间的分布符合优化目标。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]