[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908228,587,1,"单选题","(2016年)工程网络计划费用优化的基本思路是，在网络计划中，当有多条关键线路时，应通过不断缩短()的关键工作持续时间来达到优化目的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","直接费总和最大",false,{"key":16,"text":17,"correct":14},"B","组合间接费用率最小",{"key":19,"text":20,"correct":14},"C","间接费总和最大",{"key":22,"text":23,"correct":24},"D","组合直接费用率最小",true,"该题主要考察的是：工程网络计划费用优化 当有多条关键线路出现而需要同时压缩多个关键工作的持续时间时，应将它们的直接费用率之和（组合直接费用率）最小者作为压缩对象。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]