[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908227":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908227,587,1,"单选题","(2016年)单代号网络计划中，关键线路是指()的线路。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由关键工作组成",false,{"key":16,"text":17,"correct":18},"B","相邻两项工作之间时间间隔均为零",true,{"key":20,"text":21,"correct":14},"C","由关键节点组成",{"key":23,"text":24,"correct":14},"D","相邻两项工作之间间歇时间均相等","该题主要考察的是：单代号网络计划中的关键线路，如前所述，总时差最小的工作为关键工作。将这些关键工作相连， 并保证相邻两项关键工作之间的时间间隔为零而构成的线路就是关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]