[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908226":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908226,587,1,"单选题","(2015年)计划工期与计算工期相等的双代号网络计划中，某工作的开始节点和完成节点均为关键节点时，说明该工作()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一定是关键工作",false,{"key":16,"text":17,"correct":14},"B","总时差为零",{"key":19,"text":20,"correct":21},"C","总时差等于自由时差",true,{"key":23,"text":24,"correct":14},"D","自由时差为零","本题考查的是网络计划时间参数的计算。对于网络计划中以终点节点为完成节点的工作，其自由时差与总时差相等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]