[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908224":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908224,587,1,"单选题","(2011年)在建设工程施工方案一定的前提下，工程费用会因工期的不同而不同，随着工期的缩短，工程费用的变化趋势是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接费增加，间接费减少",true,{"key":16,"text":17,"correct":18},"B","直接费和间接费均增加",false,{"key":20,"text":21,"correct":18},"C","直接费减少，间接费增加",{"key":23,"text":24,"correct":18},"D","直接费和间接费均减少","直接费会随着工期的缩短而增加。间接费包括企业经营管理的全部费用，它一般会随着工期的缩短而减少。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]