[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908222":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908222,587,1,"单选题","(2009年)工程网络计划费用优化的目的是为了寻求()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","资源均衡使用条件下最低成本的计划安排",false,{"key":16,"text":17,"correct":14},"B","资源有限条件下最低成本的计划安排",{"key":19,"text":20,"correct":14},"C","工程总成本固定条件下的最优工期安排",{"key":22,"text":23,"correct":24},"D","工程总成本最低时的最优工期安排",true,"费用优化又称工期成本优化，是指寻求工程总成本最低时的工期安排，或按要求工期寻求最低成本的计划安排的过程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]