[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908219":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908219,587,1,"单选题","(2015年)某工程双代号网络计划如下图所示。当计划工期等于计算工期时，工作D的自由时差和总时差分别是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2和2",false,{"key":16,"text":17,"correct":14},"B","1和2",{"key":19,"text":20,"correct":14},"C","0和2",{"key":22,"text":23,"correct":24},"D","0和1",true,"本题考查的是网络计划时间参数的计算。D工作最早开始时间4，最晚开始时间5，最早完成时间9，总时差5-4=1，F工作最早开始时间9，D工作自由时差9-9=0。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]