[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908218,587,1,"单选题","(2010年)某工程双代号网络计划如下图所示，其中关键线路有()条。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3",{"key":23,"text":24,"correct":18},"D","4","(2）关键线路和关键工作。在关键线路法（CPM）中，线路上所有工作的持续时间总和称为该线路的总持续时间。总持续时间最长的线路称为关键线路，关键线路的长度就是网络计划的总工期。所以本题（1）-（2）-（3）-（6）-（7）时间最长，",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]