[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908214,587,1,"单选题","(2015年)单代号网络计划中，关键线路是指( )的线路。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由关键工作组成",false,{"key":16,"text":17,"correct":14},"B","相邻两项工作之间时距均为零",{"key":19,"text":20,"correct":14},"C","由关键节点组成",{"key":22,"text":23,"correct":24},"D","相邻两项工作之间时间间隔均为零",true,"本题考查的是网络计划时间参数的计算。从网络计划的终点节点开始，逆着箭线方向依次找出相邻两项工作之间时间间隔为零的线路就是关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]