[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908213,587,1,"单选题","(2010年)工程网络计划工期优化的目标是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划工期满足合同工期",false,{"key":16,"text":17,"correct":14},"B","计算工期满足计划工期",{"key":19,"text":20,"correct":14},"C","要求工期满足合同工期",{"key":22,"text":23,"correct":24},"D","计算工期满足要求工期",true,"所谓工期优化，是指网络计划的计算工期不满足要求工期时，通过压缩关键工作的持续时间以满足要求工期目标的过程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]