[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908212,587,1,"单选题","(2011年)在工程网络计划中，关键工作是指()的工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","时间间隔为零",false,{"key":16,"text":17,"correct":14},"B","自由时差最小",{"key":19,"text":20,"correct":21},"C","总时差最小",true,{"key":23,"text":24,"correct":14},"D","流水步距为零","(6）确定关键工作和关键线路。在网络计划中， 总时差最小的工作为关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]