[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908211":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908211,587,1,"单选题","(2012年)工程网络计划费用优化是通过()寻求工程总成本最低时的工期安排。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整组合直接费用率最小的关键工作的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","缩短组合直接费用率最大的关键工作的持续时间",{"key":19,"text":20,"correct":21},"C","缩短组合直接费用率最小的关键工作的持续时间",true,{"key":23,"text":24,"correct":14},"D","调整组合直接费用率最大的关键工作的逻辑关系","费用优化的基本思路： 不断地在网络计划中找出直接费用率（或组合直接费用率）最小的关键工作， 缩短其持续时间， 同时考虑间接费随工期缩短而减少的数值， 最后求得工程总成本最低时的最优工期安排或按要求工期求得最低成本的计划安排。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]