[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908210,587,1,"单选题","(2012年)在工程网络计划中，关键工作是指()的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟完成时间与最早完成时间的差值最小",true,{"key":16,"text":17,"correct":18},"B","双代号网络计划中开始节点和完成节点均为关键节点",false,{"key":20,"text":21,"correct":18},"C","双代号时标网络计划中无波形线",{"key":23,"text":24,"correct":18},"D","单代号网络计划中时间间隔为零","工作的总时差等于该工作最迟完成时间与最早完成时间之差， 或该工作最迟开始时间与最早开始时间之差， (6）确定关键工作和关键线路。在网络计划中， 总时差最小的工作为关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]