[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908207":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908207,587,1,"单选题","（2019年）下列工程项目目标控制方法中，可用来随时了解生产过程中质量变化情况的方法是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制图法",true,{"key":16,"text":17,"correct":18},"B","排列图法",false,{"key":20,"text":21,"correct":18},"C","直方图法",{"key":23,"text":24,"correct":18},"D","鱼刺图法","采用动态分析方法，可以随时了解生产过程中质量的变化情况，及时采取措施，使生产处于稳定状态，起到预防出现废品的作用，控制图法就是一种典型的动态分析方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]