[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908205,587,1,"单选题","（2019年）某工程有3个施工过程，分4个施工段，组织加快的成倍节拍流水施工，3个施工过程的流水节拍分别为4天、2天、4天，则流水施工工期为（ ）天",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":21},"C","16",true,{"key":23,"text":24,"correct":14},"D","18","（1）计算流水步距，流水步距等于流水节拍的最大公约数，即：K=min [4,2,4]=2 （2）确定专业工作队数目。专业工作队数=流水节拍\u002F流水步距。即2,1,2 于是，参与该工程流水施工的专业工作队总数n为：n=2+1+2=5? （3）确定流水施工工期。该计划中没有组织间歇、工艺间歇及提前插入，故根据公式算得流水施工工期为：T=（m+n-1）K=（4+5-1）*2=16天",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]