[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908203,587,1,"单选题","(2018年)某分部工程流水施工计划如下图所示，该流水施工的组织形式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","异步距异节奏流水施工",false,{"key":16,"text":17,"correct":14},"B","等步距异节奏流水施工",{"key":19,"text":20,"correct":14},"C","有提前插入时间的固定节拍流水施工",{"key":22,"text":23,"correct":24},"D","有间歇时间的固定节拍流水施工",true,"固定节拍流水施工是一种最理想的流水施工方式，其特点如下：（1)所有施工过程在各个施工段上的流水节拍均相等;（2)相邻施工过程的流水步距相等，且等于流水节拍;(3)专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工段上的任务;(4)各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]