[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908202,587,1,"单选题","(2016年)工程项目组织非节奏流水施工的特点是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","相邻施工过程的流水步距相等",false,{"key":16,"text":17,"correct":14},"B","各施工段上的流水节拍相等",{"key":19,"text":20,"correct":14},"C","施工段之间没有空闲时间",{"key":22,"text":23,"correct":24},"D","专业工作队数等于施工过程数",true,"该题主要考察的是：非节奏流水施工特点，非节奏流水施工特点：(1)各施工过程在各施工段的流水节拍不全相等；(2)相邻施工过程的流水步距不尽相等；(3)专业工作队数等于施工过程数；(4)各专业工作队能够在施工段上连续作业，但有的施工段之间可能有空闲时间。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]