[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908201,587,1,"单选题","（2017年考题）其工程有3 个施工过程,分为4 个施工段组织流水施工。流水节拍分别为2、3、4、3 天；4、2、3、5 天；3、2、2、4 天。则流水施工工期为（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":14},"C","20",{"key":22,"text":23,"correct":24},"D","21",true,"考查流水施工组织，非节奏流水施工工期的计算&mdash;大差法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]