[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908199,587,1,"单选题","(2010年)固定节拍流水施工的特点之一是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","专业工作队数大于施工过程数",false,{"key":16,"text":17,"correct":14},"B","施工段之间可能存在空闲时间",{"key":19,"text":20,"correct":21},"C","流水节拍等于流水步距",true,{"key":23,"text":24,"correct":14},"D","流水步距数等于施工过程数","固定节拍流水施工是一种最理想的流水施工方式，其特点如下：①所有施工过程在各个施工段上的流水节拍均相等；②相邻施工过程的流水步距相等，且等于流水节拍；③专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工段上的任务；④各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]