[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908195,587,1,"单选题","(2009年)某分部工程划分为4个施工过程、3个施工段，组织加快的成倍节拍流水施工，如果流水节拍分别为6、4、4、2天，则流水步距为()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","6","成倍节拍流水施工的特点如下： 1)同一施工过程在其各个施工段上的流水节拍均相等；不同施工过程的流水节拍不等， 但其值为倍数关系；2）相邻施工过程的流水步距相等， 且等于流水节拍的最大公约（K); 3）专业工作队数大于施工过程数， 即有的施工过程只成立一个专业工作队， 而对于流水节拍大的施工过程， 可按其倍数增加相应专业工作队数目； 4）各个专业工作队在施工段上能够连续作业， 施工段之间没有空闲时间。 K=min［6，4，4，2］=2",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]